V.C. Summer Units 2 and 3

Two new nuclear reactors were abandoned unfinished after more than $9 billion was spent. Executives were sentenced for deception connected to the failed project.

Spent before the two reactors were abandonedOver $9 billion
Evidence finding

Criminal convictions; unfinished reactors

Source documents5View sources ↗

Ask Impact Analyst

Ask about the numbers or evidence. Keep the conversation going with follow-up questions.

By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy

Impact Analyst

V.C. Summer Units 2 and 3

What would you like to understand?

Answers use this case’s sources and notes. They do not search the web.

AI answers can be wrong. Check the sources. Enter to send; Shift+Enter for a new line.

Privacy and sharing

By sending, you agree that Google Gemini can process your question and this case’s public notes. We save the conversation privately for review. Leave out private personal details.

Nothing is published automatically. Keep the saved reference if you want to request deletion. Read the privacy policy.

Reviewed answers

How long did the deception go on?

The SEC describes deception from 2015 through 2017. A dated internal warning on April 28, 2015 questioned the construction schedule and whether the project would qualify for federal tax credits. Bechtel delivered another warning in October 2015. The project was abandoned in July 2017, about 27 months after the April warning. That chronology comes from the SEC’s civil complaint. DOJ’s later sentencing report confirms specific criminal misconduct by four executives and describes information withheld from regulators in late 2016. The $9 billion headline covers total project spending. Estimating what earlier intervention could have saved requires dated payments, cancellation costs, recoveries and the value of work that could still be used.

Reviewed 2026-11-09

What was the money for?

Build two additional nuclear power reactors at the V.C. Summer site.

Amount discussed in this caseOver $9 billion

More than $9 billion was spent on Units 2 and 3 before they were abandoned in 2017. This is combined utility project spending, not a court finding that all of it was stolen.

Exact amount, time period and source wording

More than $9 billion of project spending before abandonment; combined utility expenditure, not a criminal loss finding

Period: 2017

Putting the amount in context

0 of 2

new reactors completed before abandonment

Neither of the two planned new reactors was finished before the project was abandoned.

What this comparison means: Zero completed reactors does not mean zero work or assets. The older, operating Unit 1 is not part of this count.

How we calculated this and where it comes from

0 completed / 2 planned new reactors

Do not imply the existing Unit 1 was unfinished. Spending includes work and assets; zero completed reactors is not a valuation of everything built or evidence all spending was stolen.

What actually happened?

The SEC describes public deception from 2015 through 2017. Internal warnings were documented by April 28, 2015, followed by an independent assessment in October 2015. The project was abandoned in July 2017, about 27 months after that April warning. Units 2 and 3 remained unfinished. A June 2026 update describes a possible restart under study, with an investment decision targeted for early 2028.

Keep in mind: The existing Unit 1 is separate and operates. Unfinished construction can still contain usable assets.

Read the detailed findings

The SEC complaint describes deception from 2015 through 2017. An April 28, 2015 internal memorandum questioned the schedule and tax-credit eligibility. Bechtel presented an independent warning in October 2015. Publicly misleading progress claims continued in 2016 and 2017, and the project was abandoned in July 2017, about 27 months after the April warning. DOJ later reported four executives sentenced for misconduct connected to the project. The SEC chronology is an allegation in its civil complaint; DOJ convictions establish specific criminal conduct. Separate utility records describe a conditional restart study. A January 2019 regulator filing reports SCE&G’s 55% share of project cash flow by year from 2007 through 2017, separately from capitalized interest. The imported year rows sum to $4,551,186,000 before $85,602,000 of separately listed undated negative transfers. Annual timing limits an exact within-year cutoff.

Reported status: Two reactors abandoned unfinished in 2017. Santee Cooper's June 2026 update describes renewed feasibility work with a target final investment decision in first-quarter 2028, not a completed restart.

The $9 billion is total project expenditure, not a finding that the entire amount was stolen. The operating Unit 1 is separate from unfinished Units 2 and 3.

Can we follow the payments?

A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.

Payment records and reporting periods · reviewed November 9, 2026

What could a 3-month funding checkpoint have changed?

Trace the money that went out after a checkpoint. The Receipts Act could require independent progress approval before the next funding release.

Gross payments potentially stopped under these assumptions$2.38 billion – $2.85 billion

Assumes review could prevent 100% of later spending. This includes payments for real work. Actual savings depend on which costs were avoidable, contract obligations, recoveries and assets kept.

V.C. Summer Units 2 and 3 ↗

SCE&G’s 55% ownership interest only. Restated annual project cash flow for 2007–2017, reported in thousands of dollars.

Construction start month
Mar 2013
Funding checkpoint
Jun 2013
Cash spending definitely after it
$2,378,375,000
In a reporting period crossing it
$473,181,000

11 annual cash-flow records · individual payment dates remain to be collected

Inspect the amounts, scope and source documents

The filing separately lists $85.602 million in undated negative transfers. These are not new cash outflows and cannot be assigned to the before/after windows. Printed totals differ by about $1,000 because source values are rounded.

The cash-flow schedule aggregates payments by year. Amounts in a year containing the checkpoint remain a timing range; no even-spending assumption is used.

Santee Cooper’s separate 45% share is outside these records. The schedule also separates $173.009 million of capitalized interest from cash flow.

Cancellation costs, usable assets, recoveries and payments already legally owed have not been valued. The gross post-checkpoint amount is not established fraud or net savings.

The construction source gives March 2013. A month-start convention sets the three-month checkpoint in June 2013. Annual timing ranges are unchanged by the day selected within June.

The 2019 filing removed $6,663,117 of consulting, executive-bonus and Bechtel costs, plus associated interest. This is a restated cost-recovery schedule rather than an unadjusted bank ledger.

Payment dates and reporting periods
RecordPayment date or reporting windowIncluded amount
Record 1Jan 1, 2007 – Dec 31, 2007$21,723,000
Record 2Jan 1, 2008 – Dec 31, 2008$100,876,000
Record 3Jan 1, 2009 – Dec 31, 2009$339,256,000
Record 4Jan 1, 2010 – Dec 31, 2010$397,334,000
Record 5Jan 1, 2011 – Dec 31, 2011$335,397,000
Record 6Jan 1, 2012 – Dec 31, 2012$505,044,000
Record 7Jan 1, 2013 – Dec 31, 2013$473,181,000
Record 8Jan 1, 2014 – Dec 31, 2014$458,200,000
Record 9Jan 1, 2015 – Dec 31, 2015$603,719,000
Record 10Jan 1, 2016 – Dec 31, 2016$813,749,000
Record 11Jan 1, 2017 – Dec 31, 2017$502,707,000

The lower amount uses records entirely after the checkpoint, counting indistinguishable repeated rows once. The upper amount also includes periods crossing the checkpoint and unresolved repeated rows. Amounts are never spread evenly across unknown payment dates. Missing records remain outside the total. The selected review date may be later than the first warning.

Complete invoice-to-payment links

Whole amount shownOver $9 billion
Invoice
What was charged.
Payment record
What was paid.
Delivery record
What was received.
0% traced to invoices and payments in this file0% of the stated Over $9 billion is linked here to an invoice and payment record. $0 is linked to invoices and payments; $0 also has delivery acceptance. $9,000,000,000 has no matched invoice and payment in this case file.

Invoice + payment record

$0 linked here

No matching invoice and payment records have been added to this file.

The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.

0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.

Help make invoices, payments and proof of delivery public.

Support the Receipts Act
How this is measured and which records are linked

Dated payment or cash-flow records are shown separately on this page. Invoice-to-payment coverage measures this collection only and requires linked invoice documents for the same scope. More than $9 billion of project spending before abandonment; combined utility expenditure, not a criminal loss finding. Preserve the source qualifier: this is not an exact spending denominator.

Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.

Invoice, payment and delivery linked
$0
Invoice and payment linked; delivery not linked
$0
No matched invoice and payment in this file
$9,000,000,000

0 matching invoice/payment records; 0 also link to delivery.

No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.

What is still missing?

How much bought usable construction, how much was recovered, and what charges remained with customers?

Which records would help answer this?

Criminal findings prove specific misconduct; they do not supply a complete, publicly reconciled ledger of all project spending, recoveries, ratepayer charges and usable assets. Dated spending records are imported on this page. The underlying invoice copies, independently accepted milestones, remaining payer scopes and recoveries still need to be connected. Payment timing by itself does not identify avoidable cost.

  • Connect federal reimbursements and utility payments to invoices, work packages and accepted engineering milestones.
  • Publish final termination costs, recovery amounts and the disposition or reuse of equipment and facilities.
  • Separate taxpayer funding, ratepayer charges and private investment in a reconciled ledger.

These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.

Can we estimate how much was wasted or stolen?

This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.

Sources and research notes (5 documents)

These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.

  1. DOJ: Fourth and final V.C. Summer executive sentenced

    justice.gov · 2024-11-21

  2. Idaho National Laboratory: Potential Cost Reduction, section 3.2 (DOE OSTI repository)

    osti.gov · 2025

  3. Santee Cooper: MOU milestones and target investment decision

    newsroom.santeecooper.com · 2026-06-30

  4. SEC complaint against SCANA et al., paragraph 2 (project expenditure allegation)

    sec.gov · 2020-02-27

  5. PSC filing, restated project cash flow, page 4

    dms.psc.sc.gov · 2019-01-18