Mississippi / Federal
Kemper coal-gasification and carbon-capture project
The Kemper project abandoned its planned coal-gasification and carbon-capture operation. The plant continued generating electricity using natural gas.
Promised technology abandoned
Ask Impact Analyst
Ask about the numbers or evidence. Keep the conversation going with follow-up questions.
By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy
What was the money for?
Demonstrate coal-based electricity generation with carbon capture.
The Energy Department had reimbursed about $382 million by January 2017. That federal support is separate from the much larger total cost of the plant.
Exact amount, time period and source wording
DOE reimbursements to Southern, not the full privately financed plant cost
Period: 2017-01
Putting the amount in context
planned carbon-capture rate for the abandoned approach
The planned coal-based process aimed to capture 65% of its carbon dioxide. That approach was abandoned while natural-gas generation continued.
What this comparison means: The 65% was a goal, not a measured result. The $382 million is a dated federal reimbursement total, not the full plant cost.
How we calculated this and where it comes from
65% planned capture; coal gasification and capture subsequently abandoned
The natural-gas power plant continued operating. $382M is the federal reimbursement snapshot, not total project cost or a calculated loss.
What actually happened?
Coal-gasification operations were suspended in June 2017. The facility was operated as a natural-gas power plant.
Keep in mind: The natural-gas plant remained usable. Federal support, total plant cost and any loss are different amounts.
Read the detailed findings
DOE OIG reported approximately $382 million reimbursed by January 2017. DOE and EIA document abandonment of the gasification approach and operation as a natural-gas plant.
Reported status: Coal-gasification operations suspended in June 2017; plant was operated as natural-gas generation.
The approximately $7.5 billion total plant cost is broader than federal taxpayer support. These sources establish no fraud adjudication.
Can we follow the payments?
A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.
Payment records and reporting periods · reviewed November 9, 2026
What could a 3-month funding checkpoint have changed?
Trace the money that went out after a checkpoint. The Receipts Act could require independent progress approval before the next funding release.
Assumes review could prevent 100% of later spending. This includes payments for real work. Actual savings depend on which costs were avoidable, contract obligations, recoveries and assets kept.
Kemper federal reimbursements ↗
Approximate DOE reimbursements to Southern through January 2017. Federal support only; private plant spending is outside this record.
- Original cooperative-agreement month
- Feb 2006
- Funding checkpoint
- May 2006
- Cash spending definitely after it
- $0
- In a reporting period crossing it
- $382,000,000
1 cumulative reimbursement total · individual dates remain unavailable
The source gives a cumulative amount inside a broad date window. A range starting at $0 means payment timing is unresolved. A $0 result after source coverage ends means later payments are uncollected.
Inspect the amounts, scope and source documents
The source reports approximately $382 million. It does not allocate reimbursements by year or by the 2008 relocation.
The default range is $0–$382 million because the source window crosses the checkpoint.
No post-report reimbursement records are included. A zero result after the report does not establish that later spending stopped.
OIG did not assess cost allowability in this inquiry. The natural-gas plant and useful work require separate valuation.
| Record | Payment date or reporting window | Included amount |
|---|---|---|
| Federal reimbursements | Feb 1, 2006 – Jan 31, 2017 | $382,000,000 |
The lower amount uses records entirely after the checkpoint, counting indistinguishable repeated rows once. The upper amount also includes periods crossing the checkpoint and unresolved repeated rows. Amounts are never spread evenly across unknown payment dates. Missing records remain outside the total. The selected review date may be later than the first warning.
Payment-record search · Cumulative reimbursements added
DOE OIG reports approximately $382 million reimbursed through January 2017 under a cooperative agreement initially awarded in February 2006.
Still needed Collect the reimbursement dates and allowable-cost review. The planned $270 million federal share is not an earlier cash-payment observation.
Reviewed November 9, 2026
Complete invoice-to-payment links
- Invoice
- What was charged.
- Payment record
- What was paid.
- Delivery record
- What was received.
Invoice + payment record
$0 linked hereNo matching invoice and payment records have been added to this file.
The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.
0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.
Help make invoices, payments and proof of delivery public.
Support the Receipts ActHow this is measured and which records are linked
This file currently links summary-level sources, with no itemized invoice-to-payment records registered against this amount. The pie measures this collection only. DOE reimbursements to Southern, not the full privately financed plant cost.
Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.
- Invoice, payment and delivery linked
- $0
- Invoice and payment linked; delivery not linked
- $0
- No matched invoice and payment in this file
- $382,000,000
0 matching invoice/payment records; 0 also link to delivery.
No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.
What is still missing?
Which federally funded equipment and work delivered the promised capture capability, and what was reused?
Which records would help answer this?
Federal reimbursement, company construction cost, ratepayer recovery and usable gas-generation assets are different accounts. No complete invoice-to-promised-carbon-capture output reconciliation is established by this source set.
- Connect federal reimbursements and utility payments to invoices, work packages and accepted engineering milestones.
- Publish final termination costs, recovery amounts and the disposition or reuse of equipment and facilities.
- Separate taxpayer funding, ratepayer charges and private investment in a reconciled ledger.
These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.
Can we estimate how much was wasted or stolen?
This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.
Sources and research notes (3 documents)
These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.
- DOE OIG Information Report OIG-IR-17-03
energy.gov · 2017-03-17
- DOE Southern Company—Kemper County
energy.gov · Status includes 2017-06-28
- EIA: Petra Nova and Kemper project comparison
eia.gov · 2017