GPS Next Generation Operational Control System (OCX)

The Space Force cancelled a new ground-control system for the Global Positioning System in April 2026. It had accepted the system under the contract in July 2025, but later integrated tests found major problems.

Reported program cost$6.27 billion
Evidence finding

Cancelled after failed integrated testing

Source documents5View sources ↗

Ask Impact Analyst

Ask about the numbers or evidence. Keep the conversation going with follow-up questions.

By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy

Impact Analyst

GPS Next Generation Operational Control System (OCX)

What would you like to understand?

Answers use this case’s sources and notes. They do not search the web.

AI answers can be wrong. Check the sources. Enter to send; Shift+Enter for a new line.

Privacy and sharing

By sending, you agree that Google Gemini can process your question and this case’s public notes. We save the conversation privately for review. Leave out private personal details.

Nothing is published automatically. Keep the saved reference if you want to request deletion. Read the privacy policy.

What was the money for?

Replace ground control for Global Positioning System satellites.

Amount discussed in this case$6.27 billion

The $6.27 billion is a January 2026 program-cost snapshot covering contractor funding and government testing and support. It is not the final cancellation cost or a proven loss.

Exact amount, time period and source wording

Approximate program cost including Raytheon funding to date and government testing/support, as stated by Space Force

Period: 2026-01

Putting the amount in context

Less than 1 year

between contractual acceptance and cancellation

Acceptance in July 2025 was followed by cancellation on April 17, 2026, less than a year later.

What this comparison means: Contractual acceptance is not proof of operational readiness. Cancellation does not establish that the entire program cost was fraud or loss.

How we calculated this and where it comes from

July 2025 contractual acceptance → April 17, 2026 cancellation

Contractual acceptance did not demonstrate successful integration or operational readiness. Do not equate cancellation with a $6.27B fraud finding.

What actually happened?

The system was cancelled on April 17, 2026 because it could not deliver needed capability in time at acceptable risk. Existing ground control is being upgraded instead.

Keep in mind: Acceptance under a contract did not mean the system was ready to operate. Final costs and reusable assets are not established here.

Read the detailed findings

Space Force said OCX could not deliver needed capabilities on an operationally relevant timeline at acceptable risk, despite contractual acceptance of the system in July 2025.

Reported status: Cancelled April 17, 2026 after integrated testing found major issues; existing GPS ground control is being upgraded instead.

This is a January 2026 program-cost snapshot, not the final terminated-program loss; later figures may include different dates and scope.

Can we follow the payments?

A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.

Payment records and reporting periods · reviewed November 9, 2026

What could a 3-month funding checkpoint have changed?

Trace the money that went out after a checkpoint. The Receipts Act could require independent progress approval before the next funding release.

Gross payments potentially stopped under these assumptions$0 – $4.42 billion

Assumes review could prevent 100% of later spending. This includes payments for real work. Actual savings depend on which costs were avoidable, contract obligations, recoveries and assets kept.

GPS OCX reported expenditures ↗

Reported OCX expenditures of $4.4216 billion through February 10, 2020. Separate from the later $6.27 billion program-cost headline.

Program start month
Feb 2007
Funding checkpoint
May 2007
Cash spending definitely after it
$0
In a reporting period crossing it
$4,421,600,000

1 cumulative expenditure snapshot · individual dates remain missing

The source gives a cumulative amount inside a broad date window. A range starting at $0 means payment timing is unresolved. A $0 result after source coverage ends means later payments are uncollected.

Inspect the amounts, scope and source documents

The expenditure table distinguishes $4.4216 billion expended from $4.9502 billion appropriated and $6.2538 billion total acquisition cost. Only the expended amount enters this review.

The official report’s indexed expenditure table was available. Direct PDF downloads returned access errors during this review. The original report remains linked for independent inspection.

FY2007 is the first listed funding year. October 1, 2006 is a conservative lower date bound, not an assigned payment date.

Individual payments inside the cumulative window are unavailable. Both start and warning scenarios therefore retain a $0 lower bound.

Earlier SAR amounts are not subtracted because historical program classifications and corrections require reconciliation. Useful software, Block 0 delivery and contractual obligations remain unvalued.

Cumulative totals and their date bounds
RecordPayment date or reporting windowIncluded amount
GPS OCX programOct 1, 2006 – Feb 10, 2020$4,421,600,000

The lower amount uses records entirely after the checkpoint, counting indistinguishable repeated rows once. The upper amount also includes periods crossing the checkpoint and unresolved repeated rows. Amounts are never spread evenly across unknown payment dates. Missing records remain outside the total. The selected review date may be later than the first warning.

Payment-record search · Dated expenditure snapshot added

Reported OCX expenditures of $4.4216 billion through February 10, 2020. Separate from the later $6.27 billion program-cost headline. The expenditure table distinguishes $4.4216 billion expended from $4.9502 billion appropriated and $6.2538 billion total acquisition cost. Only the expended amount enters this review.

Still needed Obtain the individual payments or dated period totals within the $4.4216 billion snapshot and reconcile later payments, program scope and delivered work.

Reviewed November 9, 2026

Complete invoice-to-payment links

Whole amount shown$6.27 billion
Invoice
What was charged.
Payment record
What was paid.
Delivery record
What was received.
0% traced to invoices and payments in this file0% of the stated $6.27 billion is linked here to an invoice and payment record. $0 is linked to invoices and payments; $0 also has delivery acceptance. $6,270,000,000 has no matched invoice and payment in this case file.

Invoice + payment record

$0 linked here

No matching invoice and payment records have been added to this file.

The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.

0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.

Help make invoices, payments and proof of delivery public.

Support the Receipts Act
How this is measured and which records are linked

This file currently links summary-level sources, with no itemized invoice-to-payment records registered against this amount. The pie measures this collection only. Approximate program cost including Raytheon funding to date and government testing/support, as stated by Space Force.

Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.

Invoice, payment and delivery linked
$0
Invoice and payment linked; delivery not linked
$0
No matched invoice and payment in this file
$6,270,000,000

0 matching invoice/payment records; 0 also link to delivery.

No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.

What is still missing?

What did acceptance certify, what failed in testing, and what software or equipment can still be used?

Which records would help answer this?

Contractual acceptance did not demonstrate integrated operational delivery. Final termination liability, settlement, reusable software and asset disposition are not reconciled in the press release.

  • Connect the contract, work order, invoice and approval to delivered equipment or service.
  • Publish permitted acceptance and performance evidence; give independent auditors access to protected details.
  • Reconcile recovery orders, amounts collected, termination costs and reusable assets.

These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.

Can we estimate how much was wasted or stolen?

This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.

Sources and research notes (5 documents)

These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.

  1. Space Force announces OCX termination

    af.mil · 2026-04-20

  2. GAO-27-107676 Precision navigation systems

    files.gao.gov · 2026-10

  3. DoD GPS OCX December 2012 acquisition report

    esd.whs.mil · Reviewed 2026-11-09

  4. DoD December 2019 SAR, expenditure table, page 43

    esd.whs.mil · Reviewed 2026-11-09

  5. GAO 2017 weapon-program assessment, GPS OCX

    gao.gov · Reviewed 2026-11-09

Research cutoff: November 9, 2026. Older reports may not include later changes. Read our methodology.