Savannah River MOX Fuel Fabrication Facility

A nuclear fuel plant was stopped before it began operating, after costs increased and construction milestones were missed. The Energy Department reported more than $7 billion already spent.

Spent on the cancelled fuel plantOver $7 billion
Evidence finding

Cancelled project; rising costs

Source documents3View sources ↗

Ask Impact Analyst

Ask about the numbers or evidence. Keep the conversation going with follow-up questions.

By sending, you agree to share your question and this case’s notes with Google Gemini and save the conversation privately for review. Privacy

Impact Analyst

Savannah River MOX Fuel Fabrication Facility

What would you like to understand?

Answers use this case’s sources and notes. They do not search the web.

AI answers can be wrong. Check the sources. Enter to send; Shift+Enter for a new line.

Privacy and sharing

By sending, you agree that Google Gemini can process your question and this case’s public notes. We save the conversation privately for review. Leave out private personal details.

Nothing is published automatically. Keep the saved reference if you want to request deletion. Read the privacy policy.

What was the money for?

Build a facility to make mixed-oxide nuclear fuel at Savannah River.

Amount discussed in this caseOver $7 billion

More than $7 billion had been spent by the Energy Department’s May 2018 account. The separate estimate of more than $18 billion was the forecast total project cost at completion.

Exact amount, time period and source wording

DOE summary says over $7 billion already spent at cancellation; rounded lower threshold

Period: 2018-05

Putting the amount in context

0 operating plants

operating fuel plants delivered by the cancelled project

The original project did not begin operating despite more than $7 billion in reported spending.

What this comparison means: A plant that never operated is not the same as no construction or no remaining asset value.

How we calculated this and where it comes from

0 operating plants after more than $7B spent

The unfinished facility and work performed are not worth zero. This does not label the expenditure fraud.

What actually happened?

The original fuel facility project was discontinued before operations began. The cited account described missed milestones and rising costs.

Keep in mind: Cancellation does not prove fraud, and constructed assets may still have a use.

Read the detailed findings

DOE's May 2018 account describes missed construction milestones, ballooning costs and discontinuation, with a completion estimate exceeding $18 billion and more than $7 billion already spent.

Reported status: Original mixed-oxide fuel facility project discontinued before operations.

Cancellation does not establish fraud. Constructed assets may have reuse value.

Can we follow the payments?

A report can tell us the total. To follow the money, we also need to connect each bill to a payment and to what was received.

Early-intervention calculation review

What could a three-month checkpoint have saved?

Obtain monthly NNSA contractor payments, termination costs and retained-asset values. The separate $13 billion future cost avoidance after cancellation cannot be counted as money already paid.

Spent on the cancelled fuel plantOver $7 billion

A savings amount remains uncalculated until the missing evidence is assembled.

Payment-record search · Cumulative amounts; schedule missing

DOE’s 2014 audit reports about $4 billion of cumulative expenditures. A later $7 billion spending figure covers a longer period. These rounded totals do not identify the intervening payment dates.

Still needed Obtain monthly NNSA contractor payments, termination costs and retained-asset values. The separate $13 billion future cost avoidance after cancellation cannot be counted as money already paid.

Reviewed November 9, 2026

Complete invoice-to-payment links

Whole amount shownOver $7 billion
Invoice
What was charged.
Payment record
What was paid.
Delivery record
What was received.
0% traced to invoices and payments in this file0% of the stated Over $7 billion is linked here to an invoice and payment record. $0 is linked to invoices and payments; $0 also has delivery acceptance. $7,000,000,000 has no matched invoice and payment in this case file.

Invoice + payment record

$0 linked here

No matching invoice and payment records have been added to this file.

The circle shows the share of the displayed total with those records. Blue means linked here; gray means not linked here.

0% means no matching records are linked in this file. It does not describe every record the government holds or prove that money was lost or stolen.

Help make invoices, payments and proof of delivery public.

Support the Receipts Act
How this is measured and which records are linked

This file currently links summary-level sources, with no itemized invoice-to-payment records registered against this amount. The pie measures this collection only. DOE summary says over $7 billion already spent at cancellation; rounded lower threshold. Preserve the source qualifier: this is not an exact spending denominator.

Only invoice and payment records tied to this same amount and scope count. Delivery coverage also requires a linked acceptance record. A report showing a total does not count as an individual receipt.

Invoice, payment and delivery linked
$0
Invoice and payment linked; delivery not linked
$0
No matched invoice and payment in this file
$7,000,000,000

0 matching invoice/payment records; 0 also link to delivery.

No individual invoice-to-payment records are registered in this file yet. This does not establish that those records do not exist elsewhere.

What is still missing?

What did each payment buy, and which buildings, equipment or designs were reused after cancellation?

Which records would help answer this?

The cited summary distinguishes spent money from completion estimates but does not reconcile every invoice, termination payment, asset transfer or subsequent reuse.

  • Connect federal reimbursements and utility payments to invoices, work packages and accepted engineering milestones.
  • Publish final termination costs, recovery amounts and the disposition or reuse of equipment and facilities.
  • Separate taxpayer funding, ratepayer charges and private investment in a reconciled ledger.

These records have not all been assembled here. They may exist elsewhere. Personal details should stay protected.

Can we estimate how much was wasted or stolen?

This file does not establish an independent value for everything delivered. Subtracting a guessed value from a headline amount would not establish fraud. A sound estimate needs matching costs, delivered results and evidence about why any money was lost.

Sources and research notes (3 documents)

These documents support the case. A source document can describe many payments; it is not itself an itemized receipt.

  1. DOE Nuclear Power Summary, May 2018

    energy.gov · 2018-05

  2. DOE OIG Audit Report DOE-OIG-20-16

    energy.gov · 2020

  3. DOE 2014 MOX audit

    energy.gov · Reviewed 2026-11-09

Research cutoff: November 9, 2026. Older reports may not include later changes. Read our methodology.